Time Savings into Revenue: Quick Serve Restaurant Franchises

TimeSavings-Revenue_QSR.png

Franchising a quick serve restaurant can be a profitable business, but it also requires a large amount of cash up front.  If you’re looking to build a standalone building to open a quick serve restaurant, modular could be the answer to seeing a return on your investment more quickly.  Here’s how...

Modular construction can offer generous time savings when it comes to building a new restaurant.  On average, the restaurant will have their doors open and serving food to their customers three months earlier than building with conventional construction.  But how much could that really save? We used QSR’s Magazine Top 50 brands in quick service and fast casual to find out.

   

Average Yearly Sales Per Restaurant

Average Sales/Savings Opening 90 Days Early with Modular

McDonald's

 

$2,500,000

$616,438

Starbucks * 1

 

$1,048,100

$258,436

Subway *

 

$475,000

$117,123

Burger King *

 

$1,210,000

$298,356

Wendy's *

 

$1,594,000

$393,041

Taco Bell 2

 

$1,441,000

$355,315

Dunkin' Donuts *

 

$911,000

$224,630

Chick-fil-A

 

$3,064,200

$755,556

Pizza Hut 2

 

$843,000

$207,863

Panera Bread

 

$2,500,000

$616,438

KFC 2

 

$960,000

$236,712

Domino's

 

$809,200

$199,529

Sonic Drive-In *

 

$1,153,000

$284,301

Chipotle *

 

$2,472,000

$609,534

Carl's Jr./Hardee's

 

$1,330,000

$327,945

Little Caesars *

 

$815,000

$200,959

Dairy Queen

 

$1,268,100

$312,682

Arby's

 

$983,000

$242,384

Jack in the Box

 

$1,412,000

$348,164

Papa John's *

 

$1,060,000

$261,370

 

Average revenue generated in 90 days based on the top 20 quick serve and fast casual restaurants: $343,339

After the large initial investment that most quick serve restaurants require, seeing over $300,000 of revenue generated three months earlier than building with conventional construction could have a large impact on the business.

Wondering what a modular restaurant looks like?  Check out the Domino’s pizza theatre case study.